2400 Head Nursery (82’x110′) Follow 10 weeks of detail and photos of our recent 2400 Head Nursery project. Week #1 Progress: Pre-construction meetingExcavated holeDug footingsSet rebar and formsPoured pit floorsStarted on pouring pit walls Week #2 and #3 Progress: Finished pouring pit walls and columnsPoured office/load out footings and wallsConnected drain tilesBackfilledCrew worked hard to get concrete done before early snow storm.Have luxury of waiting now until weather improves. Week #4 and #5 Progress: Poured bin pads, office and load chute floorsSet precast, beams and slatsSet nursery flooringBuilding package arriving soon! Week #6, #7 and #8 Progress: Completed framingSteel work complete Week #9 and #10 Progress: Grouted precastGas piping completeElectrical wiring completeEquipment installed – feeders, feed systems, ventilation, heat and plumbingGood pressure wash and this facility is ready for pigs!